Many Voices Working for the Community Oak Ridge |
Approved April 9, 2003, Meeting Minutes
The Oak Ridge Site Specific Advisory Board (ORSSAB) held its monthly meeting on Wednesday, April 9, 2003, at the DOE Information Center in Oak Ridge, beginning at 6:00 p.m. A video tape recording of the meeting was made and may be viewed by calling the ORSSAB support office at 865-576-1590.
Members Present
Jake Alexander
Dick Berry
Jeanne Bonner
Donna Campbell, Secretary
Jenna Carignan1
Heather Cothron
Amy DeMint
Luther Gibson
Pat Hill
David Johnson1
John Kennerly
Steve Kopp
Bob McLeod
John Million
David Mosby, Chair,
Luis Revilla
George Rimel
Kerry Trammel
Charles Washington
1Student representative
Members Absent
Ben Adams
Colin Loring
Norman Mulvenon Vice Chair
Deputy Designated Federal Official and Ex-Officios Present
Dave Adler, Ex Officio, DOE-Oak Ridge Offices (DOE-ORO)
Jay Bassett, Ex Officio, Environmental Protection Agency (EPA)
Gerald Boyd, Deputy Designated Federal Officer, DOE-ORO
Pat Halsey, Federal Coordinator, DOE-ORO
John Owsley, Ex Officio, Tennessee Department of Environment and Conservation (TDEC)
Others Present
Jim McBrayer, Bechtel Jacobs Company LLC (BJC)
Pete Osborne, (BJC)
Judy Ullmann, Temp Systems
Fourteen members of the public attended the meeting.
Presentation
Mr. Adler presented an overview of the Molten Salt Reactor
Experiment (MSRE). The presentation included a historical review of the MSRE project and
an update on current and planned activities. A copy of the presentation is included as
Attachment 1.
MSRE operated at Oak Ridge National Laboratory (ORNL) from 1965
to 1969. MSRE was shut down in 1969 and the salts were drained into the three fuel drain
tanks. During routine surveillance and maintenance, uranium hexafluoride (UF6)
migration through the MSRE off-gas system to the charcoal beds was discovered. The
migration of the UF6 from the fuel tanks to other elements and the resulting
generation of fluorine gas were first detected in the 1980s. Corrective actions for the
uranium deposit removal from the charcoal beds were initiated to mitigate the risks of a
nuclear criticality at MSRE or contaminant release. The fluorine gas and UF6 in
the off-gas system was removed and collected in sodium fluoride traps. The traps are
depressurized and material removed for disposition. A record of decision was signed in
June 1998 for removal of the fuel and flush salts. Preliminary plans are in place to
demolish the facility below grade, entomb, and cap the two acre area.
Following his discussion of MSRE, Mr. Adler reviewed other
reactors in the Environmental Management (EM) Program, and he distributed a table
(Attachment 2) providing information on each reactors history, status, current
activities, decision document, remedial action/cost, and schedule.
After the presentation, the following questions were asked by
members of the Board and the public, and the following responses were given by Mr. Adler.
Question |
Response (abridged) |
Ms. Hill - Id like to review the process of
liquefying the salt with the probe. When you melt the salt in MSRE to accomplish
remediation of the reactor, wont that release volatile gases? |
The probe will heat and liquefy the salt. Uranium will be
stripped from the fuel tanks by bubbling gas through the liquid. There is an increased
risk once the salt is melted. Off-gases will be managed, monitored, and contained. The salt is hazardous to begin with, and yes, when
its melted it will be even more so. This must be done, however, to defuel the
reactor. I expect the challenge to be manageable. Weve done a lot of planning to
anticipate any problems. |
Ms. Hill - Why does it show in your handout that the
timeline for taking down all the reactors is the same? |
Thats a general timeframe; each project will start and end
independently. There will be some concurrent activity. |
Mr. Gibson - The UF6
was removed into sodium fluoride traps and
turned over to ORNL for conversion. Can you provide an update? Is this process of removing
the UF6 and fluorine gas by using the sodium fluoride traps being handled
within the EM Program? What will be the disposition of the uranium-233 from the traps?
What is the most feasible disposal? |
One of the early things we did was to build in these traps, and
we have a program in place to depressurize them. Six or seven have been done, and others
are near the pressure level at which they will be ready for depressurization. |
Mr. Gibson - What will be the disposition of the
uranium-233 from the traps? |
The activity of trapping the fluorine gas and UF6 in
sodium fluoride traps is funded by EM and implemented by ORNL. Six to seven of the sodium fluoride traps have been
depressurized to remove fluorine gas. There is a range of options for disposition of the
uranium material: re-use for medical and commercial purposes or land disposal. |
Mr. Kopp - Whats the volume of the salt youll
be removing from the fuel drain tanks? Will the material be removed from these tanks be
managed as remote- or contact-handled waste? Where will the material be stored until
ultimate disposition? |
I dont know the exact volume of the salts in the fuel drain
tanks, but the tank size is approximately 8 feet by 11 feet by 8 feet. Molten salts from
the tanks will be placed in salt cans and placed in compliant storage in existing
facilities on the reservation. It will be managed as remote-handled transuranic waste and
will ultimately be shipped to the Waste Isolation Pilot Plant. |
Mr. Kopp - Will there be any fissile material? |
At this point we will have removed as much uranium from the salt
as possible. Criticality concerns are always a part of any storage activity, so they will
be considered in planning for storage. In this situation, criticality is unlikely. |
Ms. Bonner - Will the MSRE facility be demolished to below
grade following remediation? |
Yes, 2 feet below grade. |
Ms. Bonner - How much equipment is underground? |
Piping, salt tanks, and some ancillary equipment. |
Ms. Bonner - Will the underground equipment and piping be
grouted in place? |
Yes, some will. Some equipment will be pulled out and directed
for disposal at the Environmental Management Waste Management Facility. |
Ms. Bonner - Will the cap placed over the site be
concrete? |
No, it will be a 2-acre, multilayer RCRA cap, such as those
placed over hazardous landfills. It will be a permanent entombment requiring long-term
surveillance and maintenance. |
Ms. Bonner - Who will be responsible for long-term
maintenance? |
The federal government, as part of a larger stewardship
responsibility for the Oak Ridge Reservation. The cap will be monitored by a federal
agency with oversight by the State of Tennessee and EPA. |
Mr. Trammell - Is the remote-handled salt waste already
factored into inventories planned for disposal at the Waste Isolation Pilot Plant? |
Yes. |
Mr. Trammell - What if fuel from the other reactors is
deemed remote-handled waste? |
All the other reactors have been defueled except the Tower
Shielding Facility. Its fuel will not be managed as waste; it will likely be reused
at another reactor. |
Mr. Kennerly - Is it known how the uranium is distributed
throughout the carbon in MSRE? |
Its at the front end where the flow through the system
began. |
Mr. Kennerly - Isnt that a problem? |
Its a condition we addressed very quickly to eliminate.
Ninety percent of the activity was located in the first few feet of the approximately 30
feet of tubes, so luckily it was there to be accessed. |
Ms. Hill - Do you have any idea why the carbon crusted? |
Its my understanding that after 30 years the carbon had
naturally annealed, causing a crusting. |
Mr. Million - When you grout, do you plan to fill any
voids? |
Yes. We plan to eliminate voids that promote subsidence by using
a cementitious mix that effectively provides in situ stabilization. |
Ms. Bonner - Have you used grouting before? |
Yes, at many places around the reservation. Grouting often
decreases the risk of exposure and decreases the cost of remediation over the risk and
cost of excavating and shipping waste for disposal. |
Ms. Cothron - How much and what types of contamination
will be left in place? |
The final closure of MSRE is still a subject of decision-making
under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA)
process. We believe there are 500 grams of uranium left in the charcoal and residual
amounts in the salt. This will be the main extent of contamination to be discussed with
the regulators. |
Mr. Gibson - Have you anticipated any waste loading into
grouting activities? |
The grout will not contain waste, and it will act as a barrier. |
Deputy Designated Federal Officer and Ex-Officio Comments
Mr. Boyd presented plaques of appreciation to student
representatives Jenna Carignan and David Johnson, whose terms of service on the Board
end in April.
Mr. Boyd made four announcements:
§
The reorganization of the EM Program
to better align with the Accelerated Closure Program initiative will be finalized soon
(see Attachment 3). The largest organizational change was the de-layering of managers by
elimination of three deputy positions.
§
The selection of a new DOE-ORO
Assistant Manager for EM should be announced in the next few days.
§
Work is progressing on the BJC closure
contract. It should be ready for signature by June 1.
§
If requested, a presentation on the
Depleted UF6 Program can be given at the May 14 Board meeting. The
presentation could include some discussion of conversion plants, transportation of
cylinders, and risk associated with cylinders, cylinder yards, transportation, etc. The
presentation would be very timely because a transportation plan for the UF6
cylinders is in development now. The plan calls for transporting cylinders that contain
depleted UF6 from the East Tennessee Technology Park to DOEs Portsmouth,
Ohio, facility for conversion. Parts of the plan will be classified, but a version without
the classified material will be distributed to the public.
Public Comment
None
Announcements and Other Board Business
The next Board meeting will be Wednesday, May 14, 2003, at the
DOE Information Center. The presentation will focus on impacts of the FY 2003 EM Program
Budget. (The topic was subsequently changed by the
Executive Committee to a review of the states monitoring program, as related to the
Tennessee Oversight Agreement.)
Minutes of the March 12, 2003, Board meeting were approved
without change.
The Board considered a draft letter by Mr. Alexander to Assistant
Secretary of Energy for EM Jessie Roberson, ORSSAB Endorsement of the City of
Oak Ridges Application for Renewed Annual Assistance Payments Pursuant to the Atomic
Energy Act of 1954 (Attachment 4). The Board voted to send the letter to the
Environmental Restoration Committee to add verbiage that (1) ties the letter more directly
with the Boards EM Program mission related to stewardship and land use and (2)
provides more historical background on the Oak Ridge annual assistance payments and
reasons for the current request.
Ms. DeMint reported that at its March meeting the Environmental
Restoration Committee heard a presentation on Corehole 8. Some errors in the Environmental
Restoration Committee minutes provided in the Board notebooks have been noted, and she
will ask staff to revise them. Mr. Gibson noted that one of the participants in the
committees meeting, Brian Spalding, was misidentified as Dick Spalding.
Mr. Million reported that the Stewardship Committees April
meeting was cut short because the featured presenter, Ralph Skinner, had to cancel because
of a death in the family. Mr. Gibson asked if the Stewardship Committee had any output
from reviewing the Official Use Only policies for some information provided to
the SSAB members. Mr. Million replied that the committee is continuing efforts on this
topic in the area of information management.
Mr. Gibson reported that the Waste Management Committee had
discussed some transuranic waste issues at its March 16 meeting, but the committee has not
received information requested from DOE in order for the committee to have an informed
discussion on the topic. The committee developed general comments on the Comprehensive
Waste Disposition Plan and will work on them more in April. The main focus of the April
meeting is a tour of the EM Waste Management Facility. A short business meeting in the
facilitys conference room will follow the tour.
Mr. Mosby reported that at its March 25 meeting the Executive
Committee learned that the Boards budget had been cut by DOE-Headquarters by twenty
percent. This has immediately impacted the Boards ability to send members on travel,
and requests for travel to the IT3 conference have been put on hold pending further
information on the matter from Ms. Halsey at the end of April. Ms. Halsey added that cuts
have been put into effect for all SSABs and that this issue had been discussed at the EM
SSAB Chairs Meeting held March 27-29 in Denver.
Mr. Mosby reported that at the Chairs Meeting not all boards
signed the joint recommendations on transuranic waste, so the recommendations will be sent
without unanimous agreement. The Paducah delegation requested that transmittal be delayed
until after their Boards April meeting, at which time the recommendations will be
considered. The Chairs agreed to send a letter to Assistant Secretary Roberson
transmitting results of discussions at the meeting on intersite transfer of waste and
materials. Mr. Mosby distributed a copy of the letter (Attachment 5).
Mr. Osborne made several announcements:
§
Mr. Mulvenon delivered the ORSSAB
presentation to two advanced placement environmental sciences classes at Oak Ridge High
School on April 1.
§
Mr. Berry and Mr. Kopp delivered six
presentations to ecology and chemistry classes at Farragut High School on April 8.
§
The ORSSAB FY 2002 Annual Report is at the
printers and should be mailed soon.
§
The March ORSSAB meeting will be
broadcast on Knoxville cable channel 12 on April 11 at 9:30 p.m.
§
The April ORSSAB meeting will be
broadcast on Oak Ridge cable channel 12 on April 14 at 8:30 p.m.
Mr. Revilla reported that the Board Process Ad Hoc Committee had
requested a technical edit of the ORSSAB Bylaws, but it was not ready yet. Mr. Mosby added
that a proposed change to the Bylaws that was to be presented this evening would not be
ready till the Boards May meeting.
Ms. Hill and Mr. Berry reported on the Atomic Heritage Foundation
workshop held March 26-27, 2003, at the American Museum of Science and Energy. Ms. Hill
distributed a report on the event (Attachment 6). A memo regarding the event from Mr.
Berry was distributed in the meeting notebook.
Ms. Halsey discussed the March 15 submittal of preliminary
Federal Facility Agreement (FFA) Appendix J milestones for FYs 2006-2018 (ORSSAB Incoming Correspondence Item 248). This marks the
first time DOE has supplied preliminary milestones for these out years. The
revised Appendix J supplies the initial startup of work activities, the decision document
to be signed, and the completion date. Subprojects following signing of a record of
decision are not listed because of the long timelines. Normally the March 15 submittal
comes after negotiations among the FFA parties on current milestones (in this
case FY 2003-2005). But DOE did not receive its FY 2003 allocation in the
normal timeframe, so negotiations had not taken place before the March 15 submittal. In
the text of the submittal DOE asks for the opportunity to renegotiate the Appendix J
milestones following receipt of the FY 2003 allocation.
Mr. Gibson asked DOE to comment on the public involvement
statement found in the charters for closure project core teams. Mr. Adler remarked that it
is a general statement; specific involvement activities will be defined as usual as
activities are undertaken. These include review of CERCLA documents, access to DOE project
personnel, access to regulator personnel, and involvement of the SSAB.
The meeting adjourned at 9:15 p.m.
Motions
M4/9/03.1
Ms. Campbell moved to approve the minutes of the March 12, 2003,
Board meeting. Ms. Hill seconded the motion, and the motion was approved by a vote of 15 in favor, none opposed (Mr. Alexander
and Mr. Washington were absent for the vote).
M4/9/03.2
Mr. Million moved to send Mr. Alexanders letter to the
Environmental Restoration Committee for further work. Mr. Gibson seconded the motion, and
the motion was approved by a vote of 11
in favor, 5 opposed (Mr. Alexander, Mr. Berry, Ms. Hill, Mr. Kopp, Mr. Revilla).
Mr. Washington was absent for the vote.
Respectfully submitted,
Donna L. Campbell, Secretary
DLC/plo
Attachments (6) to these minutes are available upon request from
the ORSSAB support office.
ACTION ITEMS
1. Staff
will revise the April 17 Environmental Restoration Committee minutes. Action
canceled 4/10/03 by Ms. DeMint; minutes are OK as submitted with the exception of change
regarding Brian Spalding
2. The
Environmental Restoration Committee will rework Mr. Alexanders letter. Completed
4/17/03
3. Mr.
Liedle will provide Mr. Washington with the radiological readings on the K-25 converters. Carryover item from 3/12/03