DOE Oak Ridge Operations

Questions and Answers

Section L: Instructions, Conditions, and Notices to Offerors

Question #/Section

Question

Answer

Date Posted

1. L.2(f);M.1(b)
Mr. Sloan stated there will be discussions/negotiations. Will the discussions be in the form of an oral technical presentation? In other words, does the DOE anticipate that orals will be conducted following submittal of the written proposals and prior to award?

Please clarify "oral discussions." Will there be formal oral presentations and discussions similar to the Oak Ridge M&I?

The RFP provides that either written or oral discussions will be initiated with offerors in the competitive range. The extent and nature of these discussions are a matter of the Government’s judgement. If oral discussions are held, a complete oral presentation of the entire proposal will not be required. Rather, the oral discussions, or written discussions, would concern those matters related to the offeror’s proposal that DOE requests the offeror to address, e.g., weaknesses in or clarifications to the proposal as identified by DOE. 12/15/00
2. L.16, L-16.
This section defines the small business NAICS Code as 23331, with revenues not to exceed $5million/year. Please clarify that this code applies only to a potential prime offeror and that small business team partners may be classified in whatever code best matches their role in executing the statement of work. This acquisition is unrestricted and contains no set-aside provisions. Team partners may be classified in whatever code best matches their role. This NAICS code applies to any small business that competes as a prime offeror. 11/21/00
3. L.19.
Preproposal Conference-Site Tour
A. Can the bidders send a different group of personnel to the preproposal conference and the site tours? A. Yes, you may send different attendees to the site tours and preproposal conference. 11/3/00
. B. Does the limitation of four personnel also apply to the preproposal conference? B. No. There is no limitation on attendees for the preproposal conference. 11/3/00
. C. Do we have to file the same forms for foreign nationals for the preproposal conference that are required for the site tours, since the preproposal conference is not being held on a DOE site? C. No. There will be a registration desk for sign-in at the preproposal conference, but no forms are required. 11/3/00
4. L.19(b), L-17.
Our team member companies have not made multiple submittals of their intent to propose. The site tour restriction of 4 persons per proposing entity/team is limiting when you consider the number of professional disciplines required to design, cost estimate and construct this project. Would DOE consider raising the team limit to 6 persons? DOE does not have any plans to raise the team limit for the site tours. The tour is a driving tour only with no disembarkment. All germane information from the tour will be posted on the DUF6 RFP web site. DOE feels that four is an adequate number of participants for each offeror to view the sites. 11/21/00
5. L.22. The RFP does not prohibit alternate offers as has been the case in recent DOE project procurements. Does DOE desire bidders to submit alternate offers? (Example: Fixed-price bid.) While the RFP does not prohibit alternate offers, it does not solicit alternate offers. An offer that is not responsive to the terms of the RFP may not be accpetable unless an amendment to the RFP is issued which would change the terms of the RFP and allow other offerors to propose on similar terms. See RFP provision L.22(f) and Federal Acquisition Regulation 15.206(d). 12/20/00
6. L.22(e)(8). How will the NEPA support data be evaluated? This can be very costly to prepare. Will there be any sort of point scoring of this data? The NEPA support data currently required by L.22(e)(8) will be moved from Volume I, Offer to Volume II, Technical and Business Management Proposal under Criterion 1, Technology/Design. This information will be evaluated as a part of the technical proposal consistent with Section M. In addition, the NEPA support data will be utilized by DOE to begin its responsibilities with respect to the NEPA process (10 CFR 1021.216). If any information requested to be contained in the NEPA support data (attachment L3) is considered duplicative to any other requested information contained in L.23(c), the information must first be included in the NEPA support data (attachment L3), and the offeror may choose whether to also address this information in other portions of the technical and business management proposal. The information contained in the NEPA support data (attachment L3) is to be included within the 300 page limitation specified in L.23(a)(2). This change will be included in an amendment to the RFP. 01/11/01
7. L.22(e)(6), L-21.
The RFP requests submittal of a Small Business Subcontracting Plan. If the offeror chooses a prime/sub teaming structure, major scope elements such as design and construction will likely be performed by large business team partners. In preparing the Small Business Subcontracting Plan, may pre-selected team subcontractors be excluded from the subcontracting pool on which plan goals are based? Pre-selected subcontractors may not be excluded from the subcontracting pool on which plan goals are based. The subcontracting pool must include all planned subcontracting work. 11/21/00
8. L.23
In the spirit of "environmentalism," would a submittal for this proposal via either a secure web site or CD be considered in lieu of some or all of the paper copies required in L.21? (b)(1)? In addition to environmental benefits, DOE would benefit from the ability to perform key word searches, facilitate distribution, and potentially facilitate the review process. Clause L.23 of the RFP states "Video tapes, audio tapes, and floppy discs will not be reviewed." It is DOE’s intent not to review electronically submitted information including CDs. DOE’s evaluation methods require the requested number of hard copies. Therefore, we do not anticipate a change or reduction to the number of copies. 12/08/00
9. L.23(a)(2).
We appreciate the Source Evaluation Board's 12/14/00 clarification on type size. When applied to typical proposal graphics (e.g., organization charts), we find that increasing a typical 9-point graphic font to 11 points results in graphics that no longer fit on an 8-1/2 by 11-inch page (see attached samples). We would like the SEB to consider a type size for graphics that is suitable for presenting relationships among graphic elements while still maintaining legibility. Would the 9-point Arial font shown on our samples be acceptable for use on graphics? The Offeror shall use Times New Roman 12 font, Arial 11 font, or a larger type size on all material in their proposal including graphics. Graphics which will not fit on a 8-1/2 by 11-inch page can be placed on a "fold-out" page, printed in landscape mode, or printed on two pages. 01/18/01
10. L.23(a)(2)
A. Does the Volume 2 page limit of 300 pages discussed in L.23(a)(2) include tabs, table of contents, title sheet, and index? A. Any page which contains information is included in the 300-page limit. Therefore, if tabs contain no information other than the name of the section, you do not need to count them. You must count the table(s) of contents, title sheet(s), and index(ices). 12/08/00
11. L.23(a)(2) B. In Section L.23(a)(2) you state that "type size shall not exceed 12 characters per inch average over one full line of text." Would you provide this in font point sizes. e.g. 12 point Times New Roman? Is this restriction intended to only apply to body text and not headings or graphics? B. DOE does not wish to specify a required font, but would rather allow Offerors to have the flexibility to choose. Yes, the restriction does apply to headings and graphics

Revised, 12/14/00: The Source Evaluation Board has also received many questions and comments concerning the L.23 (a)(2)(i) statement that "Type size
shall not exceed 12 characters per inch average over one full line of text." The Board has reconsidered previous answers and has determined that the sentence
should be deleted and the following substituted therefore:

"The Offeror shall use Times New Roman 12 font, Arial 11 font, or a larger type size of these two fonts."

An amendment to the RFP will be issued to reflect the new requirements for font and type size.
01/17/01
12. L.23(a)(2)(i)
A. In L.23(a)(2)(i) on page L-22 you state that the "type size shall not exceed 12 character per inch average over one line of text." Does that apply to graphics and footnotes? A. Yes.


Revised, 12/14/00: See question 10.
01/17/01
13.L.23(a)(2)(i)
B. Section L.23(a)(2)(i) states, in part, that "Type size shall not exceed 12 characters per inch average over one full line of text." Times New Roman 11 point yields an average of 15.3 characters per inch. Times New Roman 12 point yields an average of 13.5 characters per inch. The Time New Roman font size required to achieve a 12 character per inch average over one full line of text is 13 points. Would DOE, please consider using the following revised language for limiting font sizes?

The font size for all body text in the proposal shall be 11 point or large. Text lines in body text shall be spaced at no less than 1 space (single spaced). Text size used in figures, tables, and spreadsheets may be no less than 8 point, but must be clearly legible.

B. DOE does not anticipate making a change to the requirements of Section L.23.

Revised, 12/14/00: See question 10.
01/17/01
14.4-9.L.23(c)(2)(iii)
Will DOE make any of its disposal sites available for waste and conversion products disposition? If so, which sites? Disposition of all wastes and conversion products are the responsibility of the Contractor. DOE disposal sites are available for Contractor consideration. 01/11/01
15. L.23.
Clause L.23(c)(1)(iv)
Does the hundred million per year include storage (storage yards) condition upgrades? Yes. 12/13/00
16A. L.23(a)(2)(i), L-22. A. Will DOE exclude title page, table of contents, table of figures, and Acronym List from the 300 page limitation? A, B,C. The 300-page limitation includes all information (pages) of the Technical Volume II. No pages are excluded. 11/21/00
16B. L.23(a)(2)(i), L-22. B. The Key Personnel 2-page resumes are currently included in the 300 page limit? We believe it is in the DOE’s best interest for the offeror to commit those employees who fulfill the functional areas required in the RFP and those other areas that we propose as critical to the success and credibility of our approach. Including the resumes in the page limitation is a disincentive to this commitment because it forces the offeror to tradeoff 2 additional pages that could be used to more fully describe our approach in order to add each additional key person. Will DOE exempt the 2-page resumes of key personnel from the 300 page limitation?
16C. L.23(d)(2)(vi), L-27. C. This section requests an integrated project critical path schedule at the expanded WBS level. May the offeror provide a summary level schedule in this section and present the detailed schedule in an appendix outside the page limitation?
17. L.23(d)(1)(i)(D)
Section L.23, d(1)(i)(D), second sentence requests that Offerors, "Describe the proposed term of subcontracts,..." We presume ‘term’ refers to the period of performance or length of time the proposed subcontracts will be in effect. Is this correct? Yes. 12/08/00
18. L.23(d)(2)
B.2. (a) requests total cost for design of both processing facilities. RFP L.24. (f) requests separate estimates for each facility. Should WBS follow Section B.2? (a) or L.24. (f)? Section B.2 delineates the top-level proposed costs for the contract, and accompanies the Offer in Volume I of your proposal. Section L.24 provides guidance for preparation of Volume III, Cost Proposal, such that DOE can adequately evaluate the Offeror’s proposed cost. The level of WBS that the Offeror proposes in response to Section L.23(d)(2) is at its own discretion, but as requested in the RFP, should be "expanded down to a level necessary to capture all the elements of the Statement of Work". 12/13/00
19. L.23(c)(1)(iv)
Section L.23.(c).(1)(iv) states "Describe the approach for plant operations and the quantity of depleted UF6 to be processed over the life of the plant (not to exceed 25 years and assume $100M per year funding inFY2000 constant dollars) and on an annual basis during the term of the contract. This should include degree of automation, operating shifts required, and manpower projections." Section L.24(g)(4)(ii) requires that,"For the purpose of proposal preparation, the amount of funds that will be available for each fiscal year of the 5 year contract period of conversion operations and cylinder management is estimated to be $100 million in Fiscal Year 2000 dollars escalated 2% annually." Is the $100 million per year a target or a maximum? The $100M per year is the level of funding projected to be available for this project on a continuing basis. Funds availability at this level is subject to appropriation by Congress on a yearly basis. 01/30/01
20A. Clause L.23(c)(1)(iv). A. (At the pre-proposal conference) What was Don (Wierwille’s) reference to limit of less than $100M per year? A, B. The RFP states to "Assume $100M/year funding in FY2000 constant dollars on an annual basis." The annual total costs proposed for all scope under this contract during the operations period must be within the $100M/year scenario. 12/13/00
20B. Clause L.23(c)(1)(iv). B. What is the basis for establishing a maximum of $100M over 25 years (approximately $4M/year) as the total funding allowed for operations, maintenance, and cylinder management? How was this figure determined? The pre-conceptual design study by Bechtel and LLNL appear to indicate much higher costs.
21. L.23(c)(1)(iv) and L.24(g)(4)(ii)


Section L.23(c)(1)(iv) states, "Describe the approach for plant operations and the quantity of depleted UF6 to be processed over the life of the plant (not to exceed 25 years and assume $100M per year funding in FY2000 constant dollars) and on an annual basis during the term of the contract. This should include degree of automation, operating shifts required, and manpower projections. Section L.24 (g)(4)(ii) requires that, "For the purpose of proposal preparation, the amount of funds that will be available for each fiscal year of the 5 year contract period of conversion operations and cylinder management is estimated to be $100 million in Fiscal Year 2000 dollars escalated 2% annually." While the RFP places an annual funding limitation on operations, none is specified for design and construction. Moreover, the RFP does not state whether the annual funding limitation applies to a single plant, both processing facilities (Paducah and Portsmouth), or both processing facilities and all cylinder maintenance activities, including the transportation of ETTP cylinders to Portsmouth.

1. Does the annual DOE funding limitation ($100M) apply to only a single facility, thereby allowing an operating budget of $200M per year for both facilities?

2. Does DOE intend to apply an annual funding limitation during design and construction of the Paducah and Portsmouth processing facilities?

1. No. The stated annual DOE funding limitation of $100M per year during operations covers all costs performed under the contract, including operations of both sites, cylinder surveillance and maintenance, transportation of ETTP cylinders to Portsmouth, and transporting converted material to disposal site.

2. No. The successful proposer's design and construction funding cost estimate incorporated into the contract will form the basis of the Department's request to Congress for funding for design and construction. However, Congressional appropriations will govern the project's funding level(s) during the design and construction phase.

12/01/00
22. L.23(e)(7).
In Section L.23(e)(7) you list the functional areas for key personnel. Please clarify the function of Nuclear Material Management. Nuclear materials control and accountability functions are required for the management of nuclear materials stored, processed or handled in the proposed conversion facilities. 12/22/00
23. L.23(e)(9).
Section L.23(e)(9) indicates that the respondents to the RFP should address the issue of environmental justice. Is there a specific environmental justice issue(s) at Portsmouth, Paducah, or ETTP that should be addressed in the proposal response? If so, please provide a reference to this issue(s)? Environmental justice issues depend on the specifics of a particular Offeror's proposal. Offerors should identify and assess any environmental justice issues that are associated with their respective technologies and proposals. DOE is subject to Executive Order 12898 regarding environmental justice, and the US Environmental Protection Agency has responsibility for enforcement of the Order. EPA's web page for environmental justice is at http://es.epa.gov/oeca/main/ej/index.html. 12/22/00
24. L.24.
Does DOE expect separate funding types, i.e., capital and expense? Yes. DOE expects to receive line item (capital) funding for construction activities and operating (expense) funding for conversion operations activities. 01/08/01
25. L.24.
We request DOE reconsider its waste disposal approach in the RFP in order to give DOE the lowest cost, best value approach. Currently, if a proposer chooses NTS, they must use $9.00/cu ft plus a truck transportation cost to get the product from the railhead to NTS. If they are successful at negotiating and fixing a contract with another waste site for a costless than ($9/cu ft plus truck transportation cost minus the additional train transport cost to get to another site), they will be in lower cost position for their proposal. However, if this proposer wins, DOE and the tax payers will lose when the NTS per cu ft rate drops next year and they have already locked into an agreement with another disposal site. We strongly suggest that DOE level the playing field in this RFP by 1) requiring every proposer to use the assumed NTS disposal rate ($9/cu ft) and a truck rate from the railhead to NTS ($1600/waste shipment on 80,000 GVW trucks), and 2) evaluating all bidders using this same rate and 3) after award DOE should participate with the selected contractor in the negotiation and selection of the final disposal site (NTS or and other site) and the final disposal rate since DOE is the largest generator and can command the best rates. We suggest the above approach is the fairest to all bidders, provides DOE a basis for a true "apples to apples" comparison of the proposals, and ensures after the award the best value, lowest cost disposal option to DOE and the taxpayers. It is the intent of the RFP as structured to allow offerors the flexibility to propose different approaches to waste disposal and associated costs, rather than define one basis that all offerors are obligated to follow. The RFP does specify for uniformity that if the Nevada Test Site is the proposed disposal site, the Offeror shall use a disposal fee of $9/cu ft. In terms of the contract requirements, it is the Contractor’s responsibility to arrange for the disposal of wastes rather than DOE’s obligation to arrange for such. However, under the terms of the contract, DOE does have certain controls with respect to administration of the contract such as approval of the Contractor’s Waste Management Plan (D-7), and subcontract approvals under clause I.98, Subcontracts. 02/09/01
26. L.24(f).
Section L.24 (f) states that "separate estimates are required for work scope related to and/or performed at Paducah, Portsmouth, and East Tennessee Technology Park." Section L.24 (g) (1)-(6) more specifically defines the costs that are to be separately identified by activity, sub-activity and facility. Please confirm that separate costs for facility locations are required only as specifically cited in (g) (1)-(6). Sections L.24 (f) and (g) require Offerors to propose separate cost estimates for activities/sub-activities at Paducah, activities/sub-activities at Portsmouth, and activities/sub-activities at East Tennessee Technology Park. 01/08/01
27. L.24.(g)(1).
Section L.24 (g) (1) Please confirm that the estimated costs for the annual updating of the System Requirements Document should be presented in the sub-activity "system requirements" under Permitting and Design Activity. The estimated cost of the System Requirements Document should be included in the system requirements sub-activity under the Permitting and Design Activity. Proposed cost for updating the System Requirements Document should be included in the project management sub-activity for the activity phase of the project when the update is prepared. 01/08/01
28. L.24(g)(1).
Section L.24 (g) (1) lists a sub-activity "system requirements" to be separately listed in the cost estimate. Please advise if DOE has a preference under which sub-activity(ies) the estimated costs should be included for the remainder of the deliverables listed on pages C-27 and C-28, i.e., Project Quality Assurance Plan, Radiation Protection Plan, Site Security Plan, etc. The proposed cost for deliverables should be included in the most appropriate subactivity. A number of the deliverables would logically fall under project management, e.g., those listed in the question (Project Quality Assurance Plan, Radiation Protection Plan, Site Security Plan). In addition, the proposed cost for deliverables should be included in the phase of the project (design, construction, or operation) in which the deliverable is due. 01/08/01
29. L.24 (g)(4)(i) and (iv).
Section L.24 (g) (4) (i) and (iv). Please advise if the Offeror is to include in the cost of transport and disposal of uranium conversion product(UO2 or U3O8 or UF4) that it cannot beneficially reuse or sell. Yes. The estimated cost for the transport and disposal of conversion product not destined for use/reuse should be included in the transportation and disposal sub-activities. 01/08/01
30. L.24 (g)(4)(ii)
Section L.24(g)(4)(ii) requires that, "For the purpose of proposal preparation, the amount of funds that will be available for each fiscal year of the 5-year contract period of conversion operations and cylinder management is estimated to be $100 million in Fiscal Year 2000 dollars escalated 2% annually." Does the $100M ceiling include the contractor's fee, or is fee to be provided in a separate budget like DOE Program Direction? Yes, the contractor’s fee is included in the $100M per year funding. 02/05/01
31. L.24(g)(4)(iv).
The RFP states that the cost to dispose of LLW at NTS should be calculated using $9/ft3. This rate has changed recently, and will change in the future. Some companies are using a rate other than the advertised current rate. Is it DOE’s intent to have all competitors use the $9/ft3 rate for NTS disposal? Yes. 12/01/00
32. L.26.
Intention to Propose
A. Please refer to Section L of the subject RFP, Article L.26 on pages L-37 and L-38. This article contains a form on the composition and organization of the bidding team and its intent to submit a proposal in response to the RFP. ... We would like to request that the submittal of the information on the composition of the team and the business relationship between the team members be delayed. A. The purpose of the Intention to Propose form is to let DOE plan for the number of proposals and to verify that people requesting to attend the site tours plan to submit proposals. We did not anticipate that this form would solidify partnering relationships. We understand that these relationships may change before proposals are due. Please submit your Intention to Propose form based on your current information. 11/9/00
. B. On page L-37 of the DUF6 RFP the Intent to Propose asks for submittal within 10 calendar days of issue. This would mean the intent to propose is due Thursday, November 9, 2000. Is this submittal date a compliance issue, where if we did not submit our Intent to Propose by November 9th, then we would not be allowed to propose? Or can we submit our intent as soon as reasonably possible? B. The intention to propose information is "requested," and you are not precluded from submitting an offer if this information is not submitted. The purpose of the Intention to Propose form is to let DOE plan for the number of proposals and to verify that people requesting to attend the site tours plan to submit proposals. 11/10/00
. C. Do we have to file the same forms for foreign nationals for the preproposal conference that are required for the site tours, since the preproposal conference is not being held on a DOE site? C. No. There will be a registration desk for sign-in at the preproposal conference, but no forms are required. 11/3/00
33. L. Att. L.5.
The items in this attachment are numbered one through five, with a sixth item that appears to be numbered incorrectly. Should the items in this attachment be numbered one through six? The attachments to Section L are numbered L1 through L6. The attachments are as follows:

L1 - Past Performance Questionnaire and Transmittal Letter

L2 - Resume Format

L3 - NEPA Data

L4 - Tour Registration Sheet, Part 1 & 2

L5 - Management Team Questionnaire

L6 - Offeror Past Performance ES&H Information Form

11/21/00




Return to Questions and Answers Page
This page was updated 02/09/01